19.6.03

City buys 60 buses without holding tender

Bambang Nurbianto, The Jakarta Post, Jakarta

Officials of the city administration revealed on Wednesday that they are purchasing 60 buses for the busway system without holding a tender, which is a violation of a presidential decree on the procurement of goods and services for government agencies.

Head of the city transportation agency Rustam Effendi said the buses which would be used in the first 12.9-kilometers of the bus rapid transit (BRT) or busway from Blok M in South Jakarta to Kota area in Central Jakarta would be Hino and Mercedes buses.

"Yes, the procurement of the 60 buses will be from Hino and Mercedes. It (The process) is completed," Rustam told the press at City Hall, adding that the assembling plant of the buses would be PT New Armada.

The city administration has allocated Rp 50 billion for procuring the buses from the city budget. The fund is part of some Rp 117 billion which has been allocated to fund the project.

The procurement of the buses is a direct violation of Presidential Decree No. 18/2000 on the procurement of goods and services for government agencies.

Article 17, paragraph 4 of the presidential decree stipulates that the procurement of goods and services may be implemented without tender under four conditions:

* If the value of the project is not more than Rp 50 million.

* In the case of consulting services, where it is hard to find participants who meet the requirements.

* In emergency or special conditions, upon approval of the minister/head of non-ministerial institution/governor/mayor/director of state-owned companies.

* If there is only one supplying company

According to Rustam, the city administration could not hold a tender due to the shortage of time as the buses were needed within six months.

"The presidential decree allows for direct appointment in an emergency situation," said Rustam.

Governor Sutiyoso said that he was not aware of the direct appointment of the companies for the procurement of the buses. He stressed, however, that he had no objection if there was a reasonable argument behind the appointment.

"The most important thing for me is that the project is expedited," he said.

Meanwhile, chairman of the Jakarta Residents Forum (Fakta) Azas Tigor Nainggolan slammed the direct appointment of the bus suppliers, saying that there was no reason for the city not to hold a tender for procuring the buses.

"How could they say it is an emergency situation when the plan to buy the buses had already been determined last year," Tigor told The Jakarta Post.
more

10.6.03

Another Rp 32 billions

Another Rp 32b sought for controversial busway project
Bambang Nurbianto, The Jakarta Post, Jakarta

The city administration said on Monday it would need an additional Rp 32 billion for its bus rapid transit (BRT) -- or busway -- project, an admission that points to the administration's poor planning of the project.

With the additional fund, which is to be taken from the city budget, the 12.9-kilometer busway stretching from Blok M, South Jakarta, to Kota, Central Jakarta, will cost at least Rp 117 billion.

"There will be significant changes in the designs of the bus shelters and bridges connecting pavements and the shelters located on the median strip," busway project leader Irzal Djamal said.

It was the second revision of the project's budget since the plan was introduced two years ago. Initially, it was estimated that the project would only cost Rp 50 billion. The figure was revised up to Rp 85 billion late last year. The implementation of the project has also been postponed several times already.

Even with the additional fund, Governor Sutiyoso said he could not guarantee that the busway would be completed in December according to the latest schedule, as there might be technical problems.

Sutiyoso said the new design for the 29 shelters would be similar to the busway shelters in Bogota, measuring 13 meters instead of the earlier design of 5 meters, and that owing to the increased space, no air conditioners would be installed as initially planned.

As for the 21 pedestrian bridges, Sutiyoso said they would be resigned as a winding, combined staircase and ramp to provide accessibility for disabled people, instead of a straight staircase.

Irzal explained that the redesigning of the bus shelter required an additional Rp 15 billion, while the change in the bridge design needed Rp 17 billion.

He did not say how much was currently allocated toward the shelters and connecting bridges, but from the previous budget of Rp 85 billion, Rp 35 billion is allocated toward the infrastructure: Shelters, connecting bridges, separators and traffic signs. Another Rp 50 billion will be used to purchase 60 buses.

He stressed that if the busway project was launched in December, the 165 buses now running along the designated busway corridors by eight bus operators -- including state-owned public bus operator PPD, Mayasari Bakti, Steady Safe and Bianglala -- would be rerouted.

Asked if the new buses would be able to accommodate the bulk of passengers who regularly travel from Blok M to Kota, Irzal could not provide an answer, but said that 140 busway buses would be available by 2004.

He also said that the buses for the busway could not use gasoline as planned earlier, because of technical problems, and would instead run on diesel fuel. It takes eight months to process the order for gasoline-powered buses, while another four months would be needed to assemble them.

However, he guaranteed that the emission from the buses would meet the international Euro II standard for environmentally friendly vehicles.

Developed countries generally use Euro III-rated buses.
more

27.5.03

'Busway project to be operational by 2010'

Bambang Nurbianto, The Jakarta Post, Jakarta

The city administration revealed on Monday its transportation system concept -- bus rapid transit (BRT) or busway and railway -- and said it expected it to be fully operational by 2010.

The busway project, which so far only has one corridor from Blok M in South Jakarta to Kota in West Central Jakarta, will be expanded to at least 15 corridors by 2010, connecting nearly all major areas in the city. While the addition of railway tracks is expected to be implemented by 2007.

Sutanto Soehodo, a transportation consultant hired by the city administration, stressed that the main goal of the BRT-railway system was to encourage people to stop using private vehicles and instead use public transportation.

Sutanto, who is the director of the University of Indonesia's (UI) Center for Transport Study (CTS), said the concept takes into account the daily flow of people from Bogor, Depok, Tangerang and Bekasi into the city center.

"Developing a transportation system without taking into account all of Greater Jakarta would be irrational as those areas are an integral part of the city," said Sutanto after explaining his concept in front of Vice Governor Fauzi Bowo on Monday.

According to Sutanto, the BRT-railway system would be supported by transfer facilities and feeder services that would serve most areas of Jakarta and its satellite cities.

The transfer facilities will be developed at a number of railway stations to convey train passengers to the busway.

Public buses will be used to transport passengers from almost all directions of the city to busway routes.

"The busway-railway system will be integrated by the feeder services and transfer facilities that will serve major parts of the city," he added.

A diagram of the transportation concept shows that eight busway corridors, namely

  • Blok M-Kota;
  • Pulo Gadung-Hotel Indonesia traffic circle;
  • Daan Mogot-Juanda;
  • Pulo Gadung-Tanah Abang;
  • Kampung Melayu-Ancol;
  • Kampung Melayu-Cideng;
  • Pasar Minggu-Manggarai;
  • and Cileduk-Cawang,
are to be developed by 2007.

While corridors to be developed from 2007 to 2010 are
  • Kampung Rambutan-Kampung Melayu;
  • Warung Jati-Menteng;
  • Tomang-Harmoni-Pasar Baru;
  • Cakung-Pulo Gebang-Kampung Melayu;
  • Senayan-Pejompongan;
  • Lebak Bulus-Kebayoran Lama;
  • Cakung-Pulo Gadung.
It also mentions supporting factors to the transportation system, including traffic restriction measures, such as road pricing, license plate-based restrictions and the three-in-one policy that may be enforced on main roads such as Sudirman, Thamrin and Rasuna Said.

Sutanto also stated that by 2020 more corridors would be developed to link Jakarta to its satellite cities.
"The development is to anticipate the high growth of commuters," said Sutanto.

Meanwhile, head of the city transportation agency Rustam Affendi said that the concept being developed by CTS could become the main reference of the development of a transportation system in the city, but additional studies could be done to enhance the concept.

Previously, assistant to the city secretary for development affairs Irzal Djamal said that the feeder services would be of a similar standard as the main corridors, which will be served by air-conditioned buses.

Irzal, who is chairman of the busway project, said that the only difference would be that there would be no special tracks for the feeder services.

The planned feeders are:
  • Bekasi-Senayan,
  • Jati Bening-Senayan,
  • Bandara-Kota,
  • Kelapa Gading-Kota,
  • Cibubur-Blok M,
  • Depok-Blok M,
  • Pondok Labu-Blok M,
  • Ciputat- Blok M,
  • Bintaro-Blok M,
  • Cileduk-Blok M,
  • BSD-National Monument (Monas),
  • Alam Sutra-Monas,
  • Kota Modern-Monas
  • and Lippo Karawaci-Monas.
more

19.5.03

Public campaign for busway needed

Bambang Nurbianto, The Jakarta Post, Jakarta

Although busway systems have been developed successfully in many cities of the world, the city administration has been advised not to apply it without securing public support and making comprehensive preparations.

Preparations include social aspects, such as a public campaign to make sure people have adequate understanding of the new policy, and technical aspects like developing bus shelters, special lanes, traffic lights, traffic signs, and preparing feeder routes.

"The system was able to be developed successfully in many cities, because it was prepared very well. But I haven't seen the same preparations here," said Azas Tigor Nainggolan, chairman of Jakarta Residents's Forum (Fakta) last Saturday.

Tigor was among members of non-governmental organizations (NGOs) who visited Bogota in Colombia -- a city which has successfully developed the bus rapid transit or BRT -- to take part in a short course on transportation.

A similar comment came from another noted urban observer Marco Kusumawijaya, who said that without public support any development program introduced by the city administration, would end in failure.

Marco also stressed the need for the city administration to make sure that related officials have an in depth understanding of the BRT concept so that they can give a comprehensive explanation to the public.

"So far I've never heard a comprehensive concept conveyed about the busway. What I have heard are only incomplete explanations," he added. "If their explanations are seemingly only concerned with restraints, like the three-in-one and license plate-based restriction policies, people will be disappointed."

A number of world's cities which have developed busway systems, include Bogota (Columbia), Sao Paulo (Brazil), Nagoya (Japan), Taipei (Taiwan), Leeds (UK), Chicago and Honolulu (U.S.), Ottawa and Vancouver (Canada), Adelaide and Brisbane (Australia).

Sharing Marco's views, Tigor also stressed the need of public approval for the city administration program which would affect a large number of people in the city.

Tigor said if the project was implemented, it would drastically change the habits and lifestyle of Jakartans.

"Just imagine, people who usually stop a bus anywhere they like will be forced to go to bus shelters. And the people who usually go to work in their own car will have to travel on public buses," he added.

Therefore, a public campaign is very important to make the people understand the project. To find out what the public wants, he added, the city administration needs to hold a poll. If most people say yes, the project could be continued.

But Governor Sutiyoso said previously that polling was not necessary as he asserted that the majority of Jakarta people accepted the busway project.

"I believe the majority of Jakarta people will accept the project as it is designed for them, if there are people who oppose the project, it must be those who use private cars," Sutiyoso said.

Marco, however, expressed skepticism that Jakartans would support the city administration's plan to develop the BRT project which is expected to be launched later this year.

First, he said he was not sure that the city administration had a comprehensive plan to tackle transportation problems in the city. Second, many development projects in the city have ended in failure due to lack of preparation.

And third, the credibility of the city administration is very low due to rampant corruption, collusion and nepotism (KKN), with the result that many projects are not implemented professionally.

Originally, the city administration planned to launch the BRT project, known as Trans Jakarta, late last year. But it was delayed as Governor Sutiyoso realized that it needed further preparation.

Sutiyoso stressed that Trans Jakarta will be launched later this year, but many observers have expressed pessimism as his administration has to date not outlined a clear and thorough concept of the busway system.
more

9.5.03

'Busway to start in December'

Governor Sutiyoso said on Thursday that the busway program would be implemented in December.

He made the statement to reporters a day after his arrival here from a foreign visit to examine the busway systems in several major cities of South American countries, including Columbia and Mexico.

He said that he had ordered Irzal Djamal, the busway team leader, to study the busway systems in the countries and see which system would be appropriate for Jakarta.

The city administration plans to establish a 12.9-kilometer busway route between Blok M in South Jakarta and Kota in West Jakarta, utilizing 140 buses, of which 80 units will be provided by a consortium of private bus companies, a report from the administration said.

The report said that feeder services and ticketing will be operated by private companies, which will be selected later through a tender.

The feeder service will provide public transportation to take passengers from all areas of Jakarta to sections of the route, which will include Jl. Sudirman, Jl. Thamrin, Jl. Gajah Mada and Hayam Wuruk.

Along with the system, the city administration also plans to extend the three-in-one traffic policy throughout the whole day until afternoon.

The policy, which requires motorists to bring at least two passengers inside their cars, is expected to encourage people to leave their cars at home and use the public transportation.--JP more

10.4.03

Jakarta busway project infeasible

Bambang Nurbianto, The Jakarta Post, Jakarta

The busway project from Blok M in South Jakarta to Kota in Central Jakarta is financially infeasible as it only serves 12.9 kilometers of road, a transportation expert says.

Lloyd Wright of the Bogota-based Institute for Transportation and Development Policy said the first stage of a similar project in Bogota, whose territory smaller than Jakarta, covered 40 kilometers of roads.

"Jakarta is larger than Bogota, therefore its first busway project should cover more road," Wright told councillors and city administration officials on Wednesday.

Wright did not elaborate on the calculation of the project costs, but stressed the need for the city administration to extend the road covered by the bus rapid transit project before launching it.

He recommended the development of another busway running east to west. He also stressed the need to develop feeder services.

"Without adequate feeder services, passengers may not move from the old bus routes."

Wright also stressed the need to fully integrate the project with other transportation systems in order to resolve transportation problems in the city.

The Jakarta city administration has begun developing the bus rapid transit, known as the busway project since last year as part of the effort to resolve the city transportation problem.

But the project has sparked criticism from transportation experts who believe it will fail. Some even say it will worsen traffic congestion in several areas.

The project was expected to be launched late last year but was delayed due to poor planning. Trials without passengers have been underway since early this year.

The city administration allocated Rp 50.8 billion for the project last year but costs have blown out to Rp 90.25 billion.

To save public funds, Wright advised the administration to only use state funds to finance infrastructure and private money to buy buses.

Wright said there were international financial institutions who could be invited to help finance the project, but the city administration should ensure that the project was the best design.

He also stressed the need for a strong vision from senior city officials to create a good transportation system.

City administration spokesman Muhayat said Governor Sutiyoso would visit a number of cities in Latin America this month to hold a comparative study on the bus systems. The cities would include Bogota, Curittiba in Brazil, and Mexico City in Mexico.

He would leave the city on April 26 and returned on May 2.
more

3.3.03

Busway begins trial period

Preparations mount as busway begins trial period
Novan Iman Santosa, The Jakarta Post, Jakarta

The city administration finally started the trial period of its long-awaited busway project, temporarily called TransJakarta, last Friday as two trial buses made the first public appearance of an expected fleet of 60 buses to ply the route linking Blok M in South Jakarta and Kota in West Jakarta.

But many questions remain as to whether the new public transportation system will be a success or will end up as another ill-fated white elephant.

Early signs of possible failure emerged as the City Transportation Agency was forced to postpone the busway trial period several times since last October.

Experts and activists say the repeated delays are signs that the agency does not have a solid concept but officials say that it was simply because they were trying to accommodate all inputs.

"We were made aware that there were so many loopholes in the initial design so we postponed the launch of the trial period," head of the agency's traffic engineering division, Udar Pristono, told reporters on the sidelines of the trial period launch at City Hall.

"This project is aimed at providing a reliable and convenient mode of transportation for residents from the middle and lower income groups so we must prepare it well."

Ordinary buses need some 120 minutes on the 12.9-kilometer Blok M-Kota route for a round trip while the busway will only need some 90 minutes as it would run along a dedicated lane.

"Not only will passengers enjoy faster travel, they will also find it more comfortable and convenient as the buses are air-conditioned and have a reliable headway of between one and a half minutes to five minutes.

"Such a short headway means that passengers will not have to wait too long if they miss the bus while at the same time increasing the busway capacity."

The fare is set at Rp 2,500 (28 U.S. cents) while current bus fares range from Rp 900 to Rp 3,500 depending on the bus type.

Pristono said that demand on the Blok M-Kota route was about 12,600 passengers per hour in one direction.

Currently the agency is testing two different buses to see which one is better suited for the project, the Japanese Hino and German Mercedes Benz.

The Hino bus has 31 seats and the Mercedes Benz has 30 seats. Both have a capacity of 55 standing passengers each.

The buses have doors on both sides to accommodate various situations along the route. It is planned that the shelters will be in the right-hand side of the bus from Blok M until Harmoni in West Jakarta. Entering Jl. Gajah Mada in West Jakarta, the buses will use the left-hand side doors.

There will be 21 stops along the route served by 39 shelters as there are several combined shelters to serve both directions.

Busway rapid transit (BRT) is a common, widely-applied system in Latin American cities such as Bogota, the capital city of Colombia; Curitiba, a city of Brazil; and Quito, the capital city of Equador.

Governor Sutiyoso is slated to visit Bogota to observe the TransMilenio busway system, which was started on Dec. 18, 2000, some time in March.

Agency officials had visited Bogota to learn the system and implement any possible principles here.

TransMilenio's official website www.transmilenio.gov.co reveals that the first phase includes three routes totaling some 41 kilometers constructed between 1998 and 2001.

There are three five-year stages until 2016 when the system is expected to reach all districts of Bogota encompassing 387.9 kilometers.

Pristono told The Jakarta Post that TransJakarta would have a total of 12 routes when it is fully operational.

"The second route will serve the Hotel Indonesia traffic circle in Central Jakarta and Rawamangun in East Jakarta. We will study this route once the Blok M-Kota is running well," he said.

In contrast to TransMilenio's clear time frame, Pristono said he could not give a clear time frame for the project or how many kilometers of road were involved.

Further homework for city officials will be how to teach the residents to use this new system as people have to be taught to queue and buy tickets before entering the shelters.
more